Welcome to the web site dedicated to the Kwant Cowling property.

  Welcome to the PROGRESS section of the site

FLASH VIDEO VIEWS FROM THE TREES

EAST TREE --- SOUTH TREE (COMING SOON) -- STREETSIDE

Here are images illustrating how the site has changed since 2005; the most current images are at the top, oldest ones at the bottom.

PHOTOS _ _ _ _ ____ ----------------____________ VIDEO

Ladder Railing Installed (as designed by Jim K.)

Deck Stained, Bath Tile, Trim, Door Latches

Kitchen Backsplash/Faucet/Wetbar 10/25/08

Siding Final Pieces (peak)

Exterior_South_10/18/08

Master Bath Mirrors/Tile

Kitchen Lights, Fans 10/1808

Railings Installed

Appliances Installed Phase 1

Compass Spot

Exteriors 9/26/08

Countertops Installed

Bathroom Granite Template

Kitchen Tile Cabinets Sept. 25

Lighting Installed

Wood Floor Sept. 14

Fireplace Keystone

Exteriors Sept. 7

Wood Floor Sept. 5

Wood Floors Cabinets Fireplace Sept. 4

Wood Flooring through Aug. 29

Cabinets Installed

Driveway Poured - Phase 2

Fireplace Slate Cut---------------------------------------Video of Slate CNC 1-----CNC 2------CNC3

Driveway Poured - Phase 1------------------------------Video of Driveway Poured, Part 1

Exteriors (August 11)

Cabinets Arrive

Doors Hung (August 7)

Exteriors (August 6)

Excavating (August 3)

Sauna Trim Closet Loft Seat

Move Refrigerator

Cement Sidewalk

Interior Painting 2nd Coat

Exterior (July) with ramp

Retaining Walls Pickup (June 22) Construction (July 4)

Pegboard/Insulation Storage Room (June 22)

Interior Painting (June 16)

Exteriors (May 16)

Exteriors (May 4) Martha, Mom, Kids

Drywall hung --------------------------------------------Video of Drywall Hanging

Roofing started-------------------------------------------Video of Roofing Installed Part 1 -- Part 2

Siding (March 28)----------------------------------------Video of Siding Install

Exteriors (March 19)

Exteriors (March 14)

Exteriors (March 12)

Exteriors (March 6)

Exteriors (March 4)

Exteriors (March 20)

Foam Insulation Ceiling (March 20)----------------------Video of Insulation Sprayed

Exteriors (March 19)

Walvac/Radiant Heat (March 19)

Water Hook-up (March 19)

Siding Prep and Stain plus More Staining (March 8)

Window Seat/Tub Framing (March 2)

Basement Floor Sealed (March 3)

Exteriors/Window Seat/Can Lighting (Feb 24)

First Fire and Spiral Stair (Jan 21)-----------------------Video of Spiral Placed

Exteriors/Cleaning (Jan 20)

Fireplace/Long Wall/Cleaning (Jan 12)

Exteriors (Jan 5)

Prep for Basement Stain

Radiant Tubes Basement (Dec 27)

Basement Cement Poured (Dec 27)----------------------Video of Basement Cement Poured

Exterior Streetside (Dec 22)

Exteriors (Dec 11)

Radiant Tubes Basement (Dec 10)

Windows Installed (Dec 10)

Interiors (Dec. 9)

Final Beams and Roof SIPs (Dec 7)---------------------Video of Roof beams, first set

---------------------------------------------------------Video of Roof SIPs, streetside view

---------------------------------------------------------Video of Roof beams, second set

---------------------------------------------------------Video of Roofbeams, final set

---------------------------------------------------------Video of roof panel, #2, lifted, sealed, placed

---------------------------------------------------------Video of roof panel #1, lifted, sealed, place

---------------------------------------------------------Video of roof panel #3, placed and sealed

Interiors (Dec 3)

Interiors/Exterior Wrap (Dec 1)

Exterior Front Porch Beams (Nov. 23)

Windows Arrive (Nov. 21)

Exterior Front Porch Posts (Nov. 19)

OSB North South Roof (Nov. 14)

Interiors (Nov. 14)

Roof Trusses (Nov. 12)

Center North South Walls (Nov. 11)

Center North South Walls, Kitchen Roof Trusses

Roof Trusses, Garage (Nov. 8)-------------------------Video of garage ridge beam

Center/West Sloping Panels (Nov. 7)

Center Floor OSB (Nov. 5)

Center Walls (Nov. 3)

Center Floor Trusses (Nov. 2)--------------------------Video of floor trusses

Posts and Beams 1--------------------------------------Video of beams at mill (Lake City)

---------------------------------------------------------Video of Basement Post/Beam Install

---------------------------------------------------------Video Post/beam fabrication

---------------------------------------------------------Video of great room, beam installation

Wall 7

Wall 6 and Post Fittings

Wall 5--------------------------------------------------Video of SIP panel base sealed

---------------------------------------------------------Video of SIP panel tipped into place

Walls 3 & 4---------------------------------------------Video of SIP panel assembled

---------------------------------------------------------Video of SIP panel assembled part 2

Wall 2

Wall 1

SIPS Arrive---------------------------------------------Video of SIPs arriving and unloading

Fill Level 5

Fill Level 4

Geothermal Laid----------------------------------------Video of geothermal tubing laid

Rocks Removed

Fill, Third Level-----------------------------------------Video of foam insulation on foundation wall, streetside view

---------------------------------------------------------Video of fill from streestide and from south side, crane in action

Fill, Second Level, August 1, 2007----------------------Video of fill, second level, streetside

Cement Waterproofing/Drain Tile

Cement Poured: Frost Wall-----------------------------Video of cement pouring, streetside

---------------------------------------------------------Video of cement pouring, mediume shot

Cement Forms Removed-------------------------------Video of foundation forms removed

Cement Forms for Foundation Walls--------------------Video of foundation forms, streetside, wide and medium static

---------------------------------------------------------Video of foundation walls poured, medium and closeup shots

Rock Gathering

Fill, First Level------------------------------------------Video of fill, bulldozer leveling, streetside view

---------------------------------------------------------Video of fill, streetside, medium shot

Drainfield & Driveway----------------------------------Video of septic digging, streetside P.O.V.

---------------------------------------------------------Video of septic tank placed

Septic tank locations (2013 pic)

Stump Removal

Tree Clearing, July 2007--------------------------------Video of cleared site, streetside,static

Brush Clearing, June, 2007

Cutting and Clearing, May, 2007

Tree Clearing, April 2007

Meadow, April 2007

December, 2006

January, 2005

 

 

 

 

 

 

 

 

 

 

 

 

 

 


©2008 Kwant Family • Contact mainalbums